SaskPower has launched the next procurement phase for its proposed North-South Interconnection project, which would connect Saskatchewan’s northern and southern power grids.

The Crown corporation has issued a Request for Supplier Qualification to identify experienced engineering, procurement and construction contractors. They say that two companies will be shortlisted to participate in an early contractor involvement phase before a final construction contract is awarded.

“The north-south interconnection will strengthen Saskatchewan’s power system and support growing electricity demand in the north,” said Jeremy Harrison, Minister Responsible for SaskPower. “This competitive procurement process is an important step toward identifying experienced contractors with the expertise and capacity needed to deliver an infrastructure project of this scale.”

A final route has not yet been selected.

SaskPower says environmental assessments and engagement with Rightsholders and Indigenous communities are ongoing.

Local benefits and Indigenous participation will also be considered during the contractor selection process.

“Bringing qualified contractors into the process early will allow us to draw on their expertise as we further develop the project’s design, schedule, cost estimates and construction approach,” said Rupen Pandya, SaskPower President and CEO. “This is a complex project, and we remain committed to meaningful and transparent engagement with Rightsholders, Indigenous communities and other stakeholders as we work to finalize a route.”

The qualification process closes Dec. 14, with the contractor selection phase expected to continue into 2027.

SaskPower is targeting spring 2028 for awarding the construction contract.